Hi @matmaxgeds, I meant check with comms. We are updating our timelines on delivery for the new IATI Datastore. From our perspective the workload should/could be wrapped up in May. But there will be a link to the new Validator service, so you would have to ask the @IATI-techteam on the complete timeline of all services bundled coming online. Makes sense?
Actual specifications as per contract.
and something we call a Master document reflecting the progress as per contract item can be found here.
Github has a label on each of the phases:
The items left are on our list of to-do. The reason you may not see an issue in progress may very well be due to another non Datastore (OIPA that is) specific ticket being handled outside of the Datastore Project. Current ETA on staff days is estimated at 20-30 days, hence the May call for delivery.
Hope this helps!